Commissioning of hydropower plant Mireshi
We are happy to announce that we have commissioned Mireshi hydro power plant in Albania recently. It is particularly pleasing because in addition to the turbine equipment, this power plant was equipped with automation and control technology from Geppert Electric.
Over the past few months our sister company Geppert Electric has been working meticulously to develop a control system (AnyHCtrl) that is specialized and tailor-made for our turbines.
In order to be extremely flexible and to be able to respond to all customer requirements as good as possible, our system was designed in such a way that it can be used in large, medium, small and micro hydropower plants. Based on any powerful PLC manufacturer, our control system creates a hydro controller solution for now and the future. By applying an advanced preventive maintenance system, we are able to predict, eliminate and prevent unwanted events before they occur.
With the easy-to-learn and intuitive user interface, we will be able to meet all control technology requirements in the future without having to have any previous knowledge in this area.
Technical data
- Turbine type: Pelton Turbine
- Quantity: 1
- Location: Albania
- Year of construction: 2023
- Net head: 163 m
- Flow rate: 1,450 l/s
- Total output: 2,100 kW
Scope of delivery: Pelton turbine, generator, inlet pipe, main shut-off device, hydraulic power unit, automation and control technology, medium-voltage switchgear, main and self-consumption transformer